Welcome to KillTest.com

CAPM Real Exam Questions - Certified Associate in Project Management

Mar 30,2020

How to prepare for your Certified Associate in Project Management CAPM certification exam to help you move in the project management field to distinguish you from other candidates when entering the workforce? It must be great preparation materials for your Certified Associate in Project Management certification exam, we have updated CAPM real exam questions on March 28, 2020. The current version of CAPM real exam questions contain 1089 Q&As, which have been verified by Killtest professional team, we are sure that you can pass CAPM Certified Associate in Project Management certification exam in the first try. 

 

CAPM Real Exam Questions Killtest

 

CAPM Is Accredited By The Prestigious Project Management Institute (PMI)

 

It must be clear that project management is a rapidly growing profession. With the CAPM, you will be on the fast track to opportunity. We know that CAPM Certified Associate in Project Management exam recognizes your knowledge of the profession's preeminent global standard, you will stand out to employers and be poised to move ahead. The Certified Associate in Project Management (CAPM) certification is accredited by the prestigious Project Management Institute (PMI). It is considered a gateway by many to time-consuming and specialized certifications, such as the Project Management Professional (PMP) certification. 

 

You can gain and maintain your CAPM exam for Certified Associate in Project Management certification now. If you would like to manage larger projects and gain more responsibility or add project management skills into your current role, then the Certified Associate in Project Management (CAPM) is right for you. CAPM exam has 150 questions in real exam, which requires you complete in three hours. Additonally, to maintain your CAPM, you must retake the exam every five years.

 

CAPM Exam Has 13 Sections In CAPM Exam Outline

 

CAPM exam is not an easy task. You know, "The CAPM certification offers recognition to practitioners who are interested or are just starting a career in project management, as well as project team members who wish to demonstrate their project management knowledge. This certification indicates knowledge of the principles and terminology within A Guide to the Project Management Body of Knowledge (PMBOK Guide) Sixth Edition, which outlines generally recognized best practices in project management." To complete CAPM exam, you need to complete all 13 sections of CAPM exam outline.

 Introduction to Project Management (6%)

● Project Environment (6%)

● Role of the Project Manager (7%)

● Project Integration Management (9%)

● Project Scope Management (9%)

● Project Schedule Management (9%)

● Project Cost Management (8%)

● Project Quality Management (7%)

● Project Resource Management (8%)

● Project Communication Management (10%)

● Project Risk Management (8%)

● Project Procurement Management (4%)

● Project Stakeholder Management (9%)

 

CAPM Real Exam Questions Based On CAPM Exam Outline

 

CAPM real exam questions are great for your Certified Associate in Project Management certification. All the questions are written by Killtest experienced experts and answers also have been verified. These CAPM questions and answers are based on CAPM exam outline. You can check our free demo of CAPM real exam questions:

 

Which document defines how a project is executed, monitored and controlled, and closed?

A. Strategic plan

B. Project charter

C. Project management plan

D. Service level agreement

Answer: C

 

Which changes occur in risk and uncertainty as well as the cost of changes as the life cycle of a typical project progresses?

A. Risk and uncertainty increase; the cost of changes increases.

B. Risk and uncertainty increase; the cost of changes decreases.

C. Risk and uncertainty decrease; the cost of changes increases.

D. Risk and uncertainty decrease; the cost of changes decreases.

Answer: C

 

Which tool or technique is used in the Plan Scope Management process?

A. Document analysis

B. Observations

C. Product analysis

D. Expert judgment

Answer: D

 

Which tool or technique is an examination of industry and specific vendor capabilities?

A. Independent estimates

B. Market research

C. Analytical techniques

D. Bidder conferences

Answer: B

 

An input used in developing the communications management plan is:

A. Communication models.

B. Enterprise environmental factors.

C. Organizational communications.

D. Organizational cultures and styles.

Answer: B

 

Regression analysis, failure mode and effect analysis (FMEA), fault tree analysis (FTA), and trend analysis are examples of which tool or technique?

A. Expert judgment

B. Forecasting methods

C. Earned value management D. Analytical techniques

Answer: D

 

The Perform Quality Assurance process occurs in which Process Group?

A. Executing

B. Monitoring and Controlling

C. Initiating

D. Planning

Answer: A

 

Enterprise environmental factors are an input to which process?

A. Control Scope

B. Define Scope

C. Plan Scope Management

D. Collect Requirements

Answer: C

 

Which process develops options and actions to enhance opportunities and reduce threats to project objectives?

A. Identify Risks

B. Control Risks

C. Plan Risk Management

D. Plan Risk Responses

Answer: D

 

The process of establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule is known as:

A. Plan Schedule Management.

B. Develop Project Charter.

C. Develop Schedule.

D. Plan Scope Management.

Answer: A

 

Which input to the Manage Stakeholder Engagement process is used to document changes that occur during the project?

A. Issue log

B. Change log

C. Expert judgment

D. Change requests

Answer: B

 

An input to the Plan Stakeholder Management process is:

A. The project charter.

B. The stakeholder analysis.

C. A communication management plan.

D. A stakeholder register.

Answer: D

 

An input to the Plan Cost Management process is:

A. Cost estimates

B. Resource calendars

C. The project charter

D. The risk register

Answer: C

 

A technique used to determine the cause and degree of difference between baseline and actual performance is:

A. Product analysis.

B. Variance analysis.

C. Document analysis.

D. Decomposition.

Answer: B

 

The process of identifying and documenting project roles, responsibilities, required skills, and reporting relationships and creating a staffing management plan is known as:

A. Develop Project Team.

B. Manage Project Team.

C. Acquire Project Team.

D. Plan Human Resource Management.

Answer: D

 

Which type of dependency is legally or contractually required or inherent in the nature of work and often involves physical limitations?

A. Mandatory

B. Discretionary

C. Internal

D. External

Answer: A

 

During which process does a project manager review all prior information to ensure that all project work is completed and that the project has met its objectives?

A. Monitor and Control Project Work

B. Perform Quality Assurance

C. Close Project or Phase

D. Control Scope

Answer: C

 

An input to the Manage Project Team process is:

A. Work performance reports.

B. Change requests.

C. Activity resource requirements.

D. Enterprise environmental factors.

Answer: A

 

Which input provides suppliers with a clear set of goals, requirements, and outcomes?

A. Procurement statement of work

B. Purchase order

C. Source selection criteria

D. Bidder conference

Answer: A

 

A large portion of a projects budget is typically expended on the processes in which Process Group?

A. Executing

B. Planning

C. Monitoring and Controlling

D. Closing

Answer: B

0 belongs to any of them

Submit Reviews

Your content: 
Your name:  Verify Code:  feedback    
CAPM Practice Exam Q&A: 897 Updated: April 26,2024

Releated Certifications

CAPM Certification

KILLTEST CONTACT INFO

[email protected]

GMT+8: Mon-Sat 8:00-18:00

GMT: Mon-Sat 0:00-10:00